Vine Main Ellice Ann Raglan - Utility Construction 2026
Project background
Planning
Design and Construction
New water, sewer, and storm infrastructure will be installed underground. This includes new mainline pipes to be installed in the road, with a connection for each home. Sidewalk and the road surface will also be replaced to match existing conditions.
Schedule and Project Downloads
2025: October/November - Hydro Pole Relocation COMPLETE.
2026: Multi-Utility construction project is anticipated to begin in July of 2026, with work progressing until the end of the construction season in approximately November.
2027: Work will resume in the spring until the project is completed, approximately mid-summer.
Although the schedule spans two construction seasons, work in front of each home is anticipated to last a few weeks. Utilities Kingston is finalizing the design work and will procure construction services by tender. After a contractor is selected, we will publish more detailed schedule information.