Skip to main content

Utilities Kingston website

Vine Main Ellice Ann Raglan - Utility Construction 2026

Vine Main Ellice Ann Raglan - Utility Construction 2026

Project background

Utilities Kingston routinely monitors the condition of the various water, sewer, gas, hydro, and fibre assets.   Projects are selected based on the condition of the pipes etc.,  as well as other factors, to ensure that the right projects are selected for replacement.  Recently, the streets Vine, Main, Ellice, Ann and Raglan have been identified as requiring utility replacement work, including: sewer separation and water main replacement.

Planning

Multi utility design including water, sewer, gas and hydro to be coordinated with City improvements.  The project will include limited sidewalk and curb repairs / replacement, as well as surface paving.

Approval for the water work will be authorized under Utilities Kingston's Drinking Water Work Permit and Environmental Compliance Approval for Consolidated Linear Infrastructure. Municipal consent for roadwork will be obtained through the City of Kingston 

Schedule and Project Downloads

2025: October/November - Hydro Pole Relocation COMPLETE.

2026: Multi-Utility construction project is anticipated to begin in July of 2026 with work progressing until the end of the construction season in approximately November.

2027 Work will resume in the spring until the project is completed, approximately mid-summer. 

Contacts

Questions? Get in touch with our customer service team at 613-546-1181