Project background

The sewer capacity in the area of Bath Rd. and Centennial Dr. has been identified as in need of sewer capacity upgrades.   Utilities Kingston has performed capacity studies, and condition assessment work on existing assets in the Bath Rd corridor. The resulting recommendations include replacement of existing sewer force-main which was originally installed in the 1960s.  The project also includes replacement of the gravity sewer from Centennial Drive westerly to Little Cataraqui Creek. 

Planning

The project will include sewer design and capacity analysis relative to the known developments anticipated for this area.    Planning of construction work is in the very early stages and will include coordination with The City of Kingston.  It is generally expected that construction will include approximately 1km of open cut trenching to install new high density polyethylene sewer force-main.

Schedule and Project Downloads

2025:  Confirmation of project scope (Complete) 

Detailed design for selected infrastructure solution (underway)

2026: 

Construction project on Bath Rd from anticipating  12 - 16 weeks of construction impacts.

Contacts

For more information on this project please contact:

David Fegan

dfegan@utilitieskingston.com

Utilities Kingston
David Fegan, P.Eng
Utilities Engineer
85 Lappan’s Lane
Kingston, ON K7L 4X7
Office: 613-546-1181, extension 2302
Email: dfegan@utilitieskingston.com