Skip to main content

Utilities Kingston website

Watermain Relining Program

Watermain Relining Program

Project background

Relining Technology

Relining watermains allows us to rehabilitate aging pipes, while minimizing service interruption and nuisance to residents. Instead of digging up the road, we excavate ‘pits’ to access the main and work from there. The relining process involves cleaning the inside of the mains and slipping in a felt liner, coated with a resin that then hardens.

Through the construction phase, Utilities Kingston staff works with the relining contractor to resolve issues due to unanticipated underground and site conditions, and with residents to address their concerns in order to alleviate any issues as quickly as possible.

On top of being less disruptive, the low-dig cured-in-place-pipe (CIPP) lining technology reduces the road base and asphalt replacement costs when compared to conventional methods, and results in a joint-less, fully-structural replacement pipe located inside the existing pipe.

Scope of Work

The watermains in the relining program are selected by reviewing priority areas based on watermain breaks and coordinating with the City of Kingston Capital Reconstruction Program.

Completed Work Areas 2022-2023

The 2022-23 Watermain Relining Program, UK-22-29, was awarded to Fer-Pal Construction Ltd.  Work was initiated in the Fall of 2022 and   1,240 meters of watermain were lined, primarily in the Collins-Bayridge and Calvin Park residential areas.   The work under this contract is complete.

  • Bath Road: West of Station Street, and East of Collins Bay Road.  
  • McIvor Road: From Sydenham Road to the Cataraqui Kinsmen Arena Complex.
  • King Street, from Collins Bay to Victoria.
  • Victoria Street, from Mary to Elizabeth .
  • Anne Street, from Mary to Elizabeth .
  • Mary Street, from Victoria to Anne.
  • Elizabeth Street, from Victoria to Anne.
  • Westbrook Road, from Princess Street to south of Ottawa Street.
  • Byron Crescent, Norman Rogers to Norman Rogers.
  • Picard Place and Michael Grass Crescent, from Byron.
  • Van Order Drive, from Metcalfe (north leg) to Norman Rogers.

Did you know?

Underground infrastructure can be replaced using a number of methods, often divided into two major areas: conventional open cut and the less disruptive and potentially more cost-effective trenchless (or low/no dig) technologies. In addition to water main relining, Utilities Kingston also uses a pipe bursting technology - a trenchless technology that allows a new larger pipe to be installed within an old pipe, while bursting the latter.

Services affected

  • Water

Planning

2024 Watermain Relining Planning

The 2024 Watermain Relining Program, UK-24-03, was awarded trough a Contract Renewal to Fer-Pal Construction Ltd. The 2024 program is planned to complete approximately 1,400 meters of watermain as follows:

Polson Park Neighborhood

  • Richardson Drive
  • Campbell Crescent
  • Bonny Castle Court
  • Barclay Road

Lake Side area

  • Cairn Grove

Water-Lining-2024.jpg

Estimated Scope for 2025: Polson Park Neighborhood

  • Robert Wallace Drive
  • Wallace Place
  • Liddell Crescent
  • Mackenzie Crescent
  • Ross Street
  • Miles Avenue
  • Strachan Avenue

Water-Lining-2025.jpg

*Areas may  be reduced or additional areas may be added as other priority sections of watermain are identified.

Schedule and Project Downloads

Starting date of the Project in Polson Park: April 02 2024.

The construction is COMPLETED at Polson Park and Cairn Grove.

Information Updated (August 23th , 2024).

Note: Schedules will be subject to revision and updates throughout the construction season and further details will be provided. 

We recognize that the upcoming construction work in your neighbourhood may bring some disruptions and inconvenience. We sincerely thank you in advance for your understanding and patience as we undertake this project.

Contacts

For further information on the 2024 Watermain Relining Project please contact me at 613-546-1181, x 2217, or via email at lseguraserrano@utilitieskingston.com

Kind Regards

Laura Segura Serrano, Ph.D.

Project Manager