Bayridge Drive Trunk Watermain

Utilities Kingston has completed a Municipal Class Environmental Assessment (Class EA) for the Bayridge Drive Trunk Watermain. The recommended watermain route (Option A) will extend west along Coverdale Drive to the access road, north along an existing trail, extend under Bath Road and the CN Mainline, and connect to the existing watermains at Bayridge Drive and Forest Hill Drive East. The watermain is proposed to be 900 mm in diameter.

This project is being planned under the Schedule B of the Municipal Class Environmental Assessment framework. Subject to comments received as a result of this Notice, and the receipt of necessary approvals, Utilities Kingston intends to proceed with the design and construction of this project.

Project Map

The Project File report, which contains a summary of pertinent information complied during the Class EA is available online or in person at:

Utilities Kingston
85 Lappan’s Lane
Kingston, ON K7L 4X7
Mon-Fri: 8:30 a.m.-4:30 p.m.
613-546-1181, ext. 2355

Comments should be provided to Utilities Kingston on the proposal within 30 calendar days from the date of this Notice. Comments should be directed in writing to:

Stephanie MacLeod, M.A. Sc,
E.I.T., Utilities Engineer-in-Training
Utilities Kingston
85 Lappan’s Lane, P.O. Box 790
Kingston, ON K7L 4X7

If concerns arise regarding this project, please contact the individuals indicated below. If an issue arises that cannot be resolved through discussion with Utilities Kingston, a person or party may request that the Minister of the Environment make an order for the project to comply with Part II of the Environmental Assessment Act (referred to as a Part II Order), which addresses individual environmental assessment. Requests must be received by the Minister at the address below within 30 calendar days of this Notice (i.e. comments are due before November 25, 2011). A copy of the request must also be sent to Utilities Kingston. If no request is received within 30 calendar days of this Notice, Utilities Kingston will be permitted proceed to design and construction as outlined in the Project File.

Requests to the Ministry of the Environment should be directed to:

Minister of the Environment
135 St. Clair Avenue, 10th Floor
Toronto, ON M4V 1P5

For additional information, please feel free to contact the following:

Michael Troop, P.Eng., M.Eng.
Environmental Engineer
J.L. Richards & Associates Limited
863 Princess Street, Suite 203
Kingston ON K7L 5N4
mtroop@jlrichards.ca
Phone: 613-544-1424 Ext. 2231
Stephanie MacLeod, M.A.Sc., EIT
Utilities Engineer-in-Training
Utilities Kingston
85 Lappan’s Lane, P.O. Box 790
Kingston, ON K7L 4X7
smacleod@utilitieskingston.com
Phone: 613-546-1181 Ext.2355

Project Files


Bayridge Drive Trunk Watermain

Schedule B Project File

Project Downloads


Appendix A

City of Kingston Water Supply Master Plan

Appendix B

Hydraulic Modeling

Appendix C

Planning Memorandum

Appendix D

Archaeological Assessment

Appendix E

Ecological Assessment

Appendix F

Geotechnical Report

Appendix G

Opinion of Probable Cost

Appendix H

Public Notices

Appendix I

PIC Presentation Package

Appendix J

Comments and Responses from Concerned Parties