Public NoticeNotice of Commencement - Electrical Ducts on Wellington Street between Brock Street and Clarence Street and Upgrades to Electrical Vault TV12 located on Brock Street at Wellington Street |
|---|
| Details: | Utilities Kingston, on behalf of Kingston Hydro, expects to commence excavation work related to Electric Duct Structure on Wellington Street between Brock Street and Clarence Streets as early as Tuesday October 12th, 2010. There will be no road closures but we do anticipate temporary closure of one lane on Wellington Street and one lane on Brock Street. Civil work is expected to take 3 weeks and will be completed by Sunrae Construction Ltd.. Kingston Hydro crews will then commence electrical upgrades following this civil work. This Kingston Hydro work is expected to continue until the end of November. We would appreciate your cooperation and patience during this project. Please do not hesitate to contact me should you wish to discuss this project. Sincerely, Tom Brackenbury, P.Eng. Utilities Engineer Utilities Kingston Tel : 613.546.1181 ext 2394 |
|
|